The scope entails major earthwork, storm pipe, storm structures, fire line, stabilization, base, and pavement.

The typical crew size was one foreman, three operators, and three laborers. Equipment mix catered to the scope. Typical for this operation: Cat 950 loader, Cat 330 excavator, D-3 dozer, vibratory roller and tool can. The major earthwork mix was, 30 on road dump trucks, Cat 950, D-3 dozer, Vibratory roller, and tool can.

The challenge of this project was coordinating with the general contract to import and place around their Warf building. Installing 1500 to 2000 CY per day of import fill.

Location

Berth 213 Improvments

Client

Tampa Port Authority

Contract Value

$2,244,474